The Structural Insulated Panels (SIP) that were to make up the walls of the new house were due to be delivered on Tuesday. The driver brough them from Kerrville, about 5 hours away and spilled the load at 9th St and 517, less than a mile away from the site.
The general contractor was not pleased. The subcontractor's foreman was not pleased. The Manufacturer's rep on site was not pleased. I was not pleased. The only consolation is that it will not cost us anything to replace the panels. It will be a hit of no less than a week to replace the panels, even though the factory was going to put it on top priority.
The spill site:


This should be a picture of the contractors unloading the panels. As it is It's a picutre of of them loading the panels after inspeciting tham and deciding the send the entire lot back.

So. Not a very good week. Hopefully they will rebuild the panels quickly and we will be building next Tuesday.